The storm sewer installation is now complete. The contractor has continued with pavement removal, excavation, and placement of the aggregate base along the east side of IL 59 near the intersection of IL 59 and Grand Ave/Washington St.

Concrete curb and gutter placement has begun at the new school entrance off IL 59.

Light pole foundations have been installed along the proposed multi-use path where a portion of Washington St. was removed. Additionally, traffic signal foundations and conduits are being installed at the corners of IL 59 and Grand Ave/Washington St.

Thank you for your interest in the IL 59 and Grand Avenue Intersection Improvement Project. Stay tuned to the website for future updates.

Please proceed with caution through the work zone and stay alert for workers and equipment.